Stormwater
Combined Sewer Overflow 34-3 Completed in 2014, the CSO 34-3 project on Ray and 21st in Spokane is 1,030,000 gallon cast in place concrete control facility with site piping, electrical, and mechanical rooms, and odor controls. The final project will include park like setting with sidewalks, grass pavers, and plants.
Aeriel view of tank progression
Kendall Yards Stormwater Facility
Combined Sewer Overflow #6 Shadle Bluff CSO #6 Control facility is the construction of a 900,000+ gallon CSO tank with mechanical and electrical facilities, structure excavation, shoring, and roadway reconstruction. It includes 2,000+ linear feet of storm, sanitary, and sewer drainage piping, and sidewalks, and landscaping. Expected Completion November 2015
North End Wall Forming
Home Projects Contact Employee Login Home Projects Contact Employee Login